Force Majeure - continuation 19 and 20 May 2023

Force Majeure - continuation 19 and 20 May 2023

May 18, 2023

Communication to Customers of Modulazione di Punta and Modulazione a Punte Costanti

Due to the meteorological conditions in Emilia Romagna, our San Potito & Cotignola’s plant is not able to guarantee the full operation.

Therefore, according to article 17.6.2 letter a) of Code of Storage, Edison Stoccaggio notify to all Customers the continuation of the FORCE MAJEURE that caused an emergency of service, and the effect is in the gas days 19 and 20 May 2023.

Due to this in the gas days 19 and 20 May 2023 the reduction of daily available injection capacity of the hub is equal to 25%.

According to above sentence, it will be possible to insert nomination and renomination not over the capacity recalculated in proportion of the above percentage. The Escomas system and the data are updated following this reduction.

Edison Stoccaggio will update you as soon as possible on the regular operation of the hub.

=============================================================================

In 17 May 2023 the communication of force majeure informed the Customers that:

- in the gas day 17 May 2023 the reduction of daily available injection capacity of the hub is equal to 10%;

- and in the gas day 18 May 2023 the reduction of daily available injection capacity of the hub is equal to 20%.

=============================================================================